CTA-N "Short Project" Power and On-site ICT Internal Review
Wednesday 23 Jan 2019, 13:55
→
19:00
Europe/Berlin
David Bristow
(
CTAO
)
12. Concept Design for CTA On-Site ICT Infrastructure (5).pdf
Appendix 1 INFRA-DES-600-003-N P1-A0 (002).pdf
Appendix 2 INFRA-DES-600-004-N P-A0 (002) (pend LSTs).pdf
CTA Requirement Specification On-Site Networking Infrastructure v1 006.pdf
CTA Requirement Specification On-Site Power system v1 003.pdf
Review Plan On-site ICT and Power v3.pdf
Study_for_Electrical_Power_for_CTA_North_2.pdf
Contact persons
carla.crovari@cta-observatory.org
david.bristow@cta-observatory.org
1
Welcome to the Review
Speaker
:
David Bristow
(
CTAO
)
Power_ICT_Concept_Review_INTRO_21.01.19FINAL.pdf
2
Requirement specifications for the On-site ICT Networking
Speaker
:
Carla Crovari
(
CTA PO
)
Requirement specifications for On-site ICT networking v2.pdf
3
On-site ICT Concept
Speakers
:
Peter Wegner, R.Lindemann, F.Krack
(
CTA-PO
)
,
Peter Wegner
(
DESY
)
CTA-Onsite-North-Network-Review-Jan-2019-v1.pdf
4
Panel Discussion
5
Coffee Break
6
Requirement specifications for the Power distribution CTA-N Short Project
Speaker
:
Carla Crovari
(
CTA PO
)
Requirements Specifications for Power distribution for CTA-N Short Project.pdf
7
Panel Discussion